Track your project progress and communicate with our team
Project requirements discussion and site visit
Completed on: 2024-01-15
Initial design concepts and layouts
Completed on: 2024-01-22
Design approval and modifications
Completed on: 2024-02-05
Architectural drawings and floor plans
Completed on: 2024-02-20
Structural engineering and calculations
Completed on: 2024-03-10
3D renderings and virtual walkthrough
Expected: 2024-03-25
Final design approval before construction
Expected: 2024-04-10
Detailed construction drawings and specifications
Expected: 2024-04-25
Building permit application and approval
Expected: 2024-05-15
Construction supervision and quality control
Expected: 2024-06-01
Asif Mohammad Tanvir
Lead Architect
Design Team
Interior Design
Structural Engineer
Engineering